Data Center Migration Checklist: 21 Facility Checks

Before you move a whole data center, check the facility itself: racks, circuits, leases, destination power and network, the period when old and new run together, any hardware that travels, and the closing of the old site. This is a data center migration checklist of 21 facility checks in six parts, for IT heads, infrastructure managers and operations leads at mid-size companies in India and the GCC. Each check has a suggested owner, the evidence to collect and the risk if it is skipped.

Before you move a whole data center, check the facility itself: the racks, circuits, leases, destination power and network, the period when old and new run together, any hardware that travels, and the closing down of the old site. This data center migration checklist covers the facility side of that move to the cloud. It works as a data center assessment, with 21 facility checks in six parts, each with a suggested owner, the evidence to collect and the risk if it is skipped.

This guide is for IT heads, infrastructure managers and operations leads at mid-size companies in India and the GCC. They have approved a move out of an on-premises or colocated data center. If that decision is still open, start with the signs that it is time. This checklist has nothing to do with Atlassian’s Jira Data Center product.


Last reviewed 2026-11-01 by Manish Sharma.

Data Center Migration to Cloud Checklist: The Short Answer

The checks here belong to the facility, not to any one application. The application-level checks sit in our cloud migration checklist for legacy applications, so this list points to them instead of repeating them. A checklist here is a readiness review. You record what you find, name the owner, and then decide at a short gate whether a wave goes ahead. As a data center assessment, it asks whether the facility is ready, while the application checklist asks whether each system is.

How to Use the 21 Checks

First, set aside a session for the data center assessment with the infrastructure owner, the network lead and whoever holds the contracts. Then, for every row, write down what you saw, the evidence (a record, a contract page, a test result) and the person who confirmed it. So a check passes only with its evidence. Change nothing yet, because this pass is about learning where the facility stands.

Data center migration checklist: six parts, from racks, circuits and leases to decommission
Six parts hold the 21 facility checks. Part 4 applies only if hardware moves.

The owners in the tables are only suggestions, so adapt them to your team. Also, the split-site and rollback checks draw on Microsoft’s Cloud Adoption Framework. In contrast, the checks for racks, leases, moving hardware and closing the site are practice, not taken from a vendor source.

Terms used below

Colocation is renting space and power in another operator’s facility. A cross-connect is a direct cable link between two parties in the same facility, while a circuit is a leased network link and a lease is the contract for space or equipment. The split-site period is the time when the old and new sites run together.

What the Application Checklist Already Covers

Checks that look the same for one application or a whole estate sit in our cloud migration checklist for legacy applications. Then run them for each system in scope. So the table gives the check numbers in that list.

Shared check Number in the application list
Named owners; success criteria and a baseline 1, 2
Inventory with support status; supported versions 4, 5
Internal and external dependencies; hard-coded addresses; shared databases 8 to 11
Identity, encryption, residency and landing zone 12 to 15
Data path, restorable backups, cutover method, rollback plan, recovery targets 16 to 20
Test environment, tests and rehearsal 21 to 23
Post-cutover metrics against the baseline; acceptance 25, 26

Our guide to application migration to cloud gives the method for those application-level steps.

Data Center Migration to Cloud Checklist, Part 1: Racks, Circuits and Leases

Four checks establish first what you have and then what binds you. The surprises in a facility move are the ones nobody wrote down, which is why Part 1 comes first.

Check Suggested owner Evidence to collect Risk if skipped
1. Every rack, device, cable run and circuit listed with location, owner and purchase date Infrastructure lead Inventory export, with serial numbers and cabling recorded before anything is disconnected Otherwise, an undocumented device is left behind or breaks something
2. Contracts, leases, maintenance agreements and carrier circuits with notice periods and exit terms Procurement with the infrastructure lead A table of each contract, its end date, notice period and exit terms As a result, a missed notice period locks you in
3. Power, cooling and floor-space footprint of what moves and what stays, per rack Facilities lead Per-rack figures for what each rack draws and occupies The old site is left half-empty and badly balanced, or the new one is undersized
4. Equipment and lease end dates, with those that fix the order of the move marked Infrastructure lead A dated list with the fixed dates highlighted A date arrives before the system has moved
Read the contract text

An undocumented device or an unread notice period is the one that can cost a month. So read the contract text, not the summary.

Data Center Migration to Cloud Checklist, Part 2: Destination Power, Space and Network

Three checks confirm that the destination is ready before any equipment leaves. AWS’s checklist for small and mid-size businesses (1 September 2025) puts the landing zone before the first application move. The same order also makes sense for a physical destination.

Check Suggested owner Evidence to collect Risk if skipped
5. Colocation or hybrid space confirmed: rack positions, power feeds, cooling, cross-connects Infrastructure lead Written confirmation from the facility operator before equipment moves Otherwise, equipment arrives and has nowhere to go
6. Carrier circuits and site-to-site links ordered with their lead times, and tested for bandwidth and latency Network lead Order records, lead times and test results, for example bandwidth and latency So the move waits for a link that is not ready
7. The addressing, DNS and VLAN plan for the move, including whether any Layer 2 network is stretched between sites Network lead A written plan, reviewed by the network and security leads before the move A stretched network can spread one fault across both sites

A VLAN is a logical network segment on shared switches. A stretched Layer 2 network goes further: it extends one segment across two sites.

Order circuits first

Circuits can be the longest wait, so start the request before the rest of the plan is finished.

Data Center Migration to Cloud Checklist, Part 3: The Split-Site Period and Parts That Stay

Four checks cover the period when you run in two places and the components that do not move yet. Microsoft advises keeping the split short and delaying a wave until more can move together.

Check Suggested owner Evidence to collect Risk if skipped
8. An end date and an owner for the split-site period Migration lead A dated plan with a named owner As a result, the split drags on with no one answerable for ending it
9. Components that stay, each with the technical or regulatory reason and a plan Architect with compliance lead A list of each component, its reason and its plan Otherwise, a component stays by accident and nobody plans for it
10. The order of moving shared storage and network segments, before or with what depends on them Infrastructure lead A sequence showing each dependent system A system moves before the storage it needs
11. Where shared services such as identity, DNS, time and monitoring live during the split Platform lead A diagram of each service and its location in each phase A shared service fails when one site loses the other

Key Takeaway The split-site period carries risk, so set its end date before it starts.

Data Center Migration to Cloud Checklist, Part 4: Moving the Hardware

Three checks apply only if equipment physically moves to colocation. But if nothing physical moves, skip this part.

Check Suggested owner Evidence to collect Risk if skipped
12. A move plan: cable labels at both ends, asset tags, rack and unrack sequence, transport, insurance and chain of custody Infrastructure lead The written plan and an asset-tag list Cables are reconnected wrongly, or equipment goes missing
13. Access and permissions at both sites, with carrier and vendor staff on standby during the move Facilities lead Access lists and a contact sheet As a result, the move stalls at a locked door
14. A power-down and power-up order, with shutdown and startup tests Infrastructure lead The written order and test results, including shutdown and startup Otherwise, systems start in the wrong order and fail to come up
Skip this part when nothing physical moves

If every workload goes to the cloud, Part 4 does not apply. Part 6 still does.

Data Center Migration to Cloud Checklist, Part 5: Cutover Window and Facility Rollback

Three checks define the facility’s way back, so write them down before the move. Our high availability checklist, however, covers failover and recovery design separately.

Check Suggested owner Evidence to collect Risk if skipped
15. The old site stays powered, connected and under contract until each wave is validated, with a date it can be released Migration lead The release date and the contract position The way back disappears before the new site is proven
16. The read-only point and freeze window for shared storage, set before the final sync Storage lead A written window and the steps Writes continue to the old copy after the final sync
17. An agreed trigger and a named person who can order the old site back into service Migration lead with the sponsor A signed trigger and name No one can decide to go back
Keep the way back open

Releasing circuits or a lease before validation removes the way back. Keep both until each wave is signed off.

For failover and recovery design, see our high availability checklist.

Data Center Migration to Cloud Checklist, Part 6: Decommission and Sanitization

Four checks close the old site, because this is the part application checklists leave out.

Check Suggested owner Evidence to collect Risk if skipped
18. A defined stability period and a written sign-off before the old site is touched Migration lead with the sponsor A signed sign-off and the date it passed The old site is dismantled while the new one is still unproven
19. Every drive sanitized or destroyed to a named standard, with certificates Security lead Certificates by serial number Otherwise, data leaves the building on a drive
20. Equipment returned, recycled or disposed of with asset tracking and chain of custody Infrastructure lead Asset records and disposal receipts So equipment cannot be traced after it leaves
21. Contracts, leases and circuits ended, site access revoked, space and power released, records updated Procurement with the facilities lead Termination notices, as well as access removal records You keep paying for, or keep access to, a site you have left

Sanitization is making the data on a drive unrecoverable. NIST publishes SP 800-88 Rev. 2, Guidelines for Media Sanitization (September 2025, which replaced Rev. 1 of 2014). Then name the revision you follow in your records.

Key Takeaway The old site closes only after a signed stability period, and every drive leaves with a certificate.

A Short Facility Gate

Before each wave, answer three questions in writing, then check them against the evidence. The three answers close the data center assessment for that wave. The full gate pattern and the finding record are in the application checklist.

Three questions to answer in writing before each wave of a facility move
Answer all three in writing before each wave goes ahead.
1
Destination

Parts 2 and 4 have evidence, and the circuits are tested before the wave.

2
Way back

Part 5 is in place and the old site is still powered and under contract.

3
Old site

Nothing in Part 6 has started until the stability period is over.

Infrastructure advice
Talk through your migration findings with Signisys.

What This Checklist Does Not Cover

This checklist is a data center assessment of the facility, so it does not cover the application-level checks, the migration strategy or the choice of destination. It also gives no cost lines and no template file. A data center assessment for cost or capacity planning is a different piece of work. So use the evidence column as your structure and the application checklist for the rest.

For the wider picture, see how Signisys supports data center infrastructure upgrades. Our page on server and data center work adds detail. See also our IT infrastructure, networking and data center services.

FAQ: Data Center Migration to Cloud Checklist

FAQ: Data Center Migration to Cloud Checklist

What should be on a data center migration to cloud checklist?

The facility checks: racks and circuits, leases and contracts, destination power and network, the split-site period, any hardware move, the facility rollback and the closing down of the old site. So application checks belong in a separate list.

How is this different from a cloud migration checklist for one application?

An application checklist looks at one system: its dependencies, data and rollback. In contrast, this data center assessment looks at the facility those systems run in, which has contracts, circuits and physical equipment of its own.

Who should own each facility check?

The person who can confirm the evidence. For example, the tables suggest owners such as the infrastructure lead, network lead, facilities lead and procurement. So adapt them to your team.

When is the facility ready for cutover?

When the destination is ready, the way back is open and the old site is still protected, each with written evidence and a named approver.

What should we check before shutting down the old data center?

A signed stability period, a written sign-off, sanitization certificates for drives, asset tracking for equipment and notices for contracts, leases and circuits.

Do we need the hardware-moving part if everything goes to the cloud?

No. Part 4 applies only if equipment physically moves to colocation. If nothing moves, skip it and keep the rest.

Newsletter

Security Insights, Delivered.

Practical, vendor-neutral analysis of threats, tools, and architecture decisions.

Book a Consultation

A practice principal will contact you within 1 business day.

Thank you! A Signisys principal will be in touch within 1 business day.