How to Build a Landing Zone: A 7-Step Cloud Build Order

How to build a landing zone, for the IT head, CIO or cloud platform lead in India or the GCC about to set up the base that every team account sits in. Seven steps in order, from account structure and home region through identity, network, logs, guardrails and cost tags to a first pilot workload. Each step comes with why it sits where it does, a suggested owner and a done-when test, plus how to build beside running workloads.

On a cloud platform shared by many teams, how to build a landing zone comes down to seven steps in a set build order. They are account structure and home region, identity, network, central logs, guardrails, cost tags and one pilot workload. Each step rests on the one before it, and each ends with a test that shows it is done.


Last reviewed 2026-11-14 by Manish Sharma.

A landing zone is the prepared base in a cloud platform: the account structure, sign-in, network, logs and guardrails that sit in place before workloads arrive. In other words, it is a secure base for every cloud account, planned before teams move in. Order matters because each layer leans on the one under it. For example, guardrails need accounts to attach to, and logs need to run before the first guardrail blocks anything. Where teams opened accounts one by one with no shared parent, the gaps that follow trace back to this missing base. The account problems themselves, from missing owners to unshared rules, are laid out in what unplanned cloud accounts put at risk.

This guide shows how to set up a landing zone in order, for an IT head, CIO or cloud platform lead in India or the GCC. It stays provider-neutral and names no product or tool. It also gives no build-time or team-size figures.

How to Build a Landing Zone: The Build Order at a Glance

When you plan how to build a landing zone, the table gives each step an owner and a test that marks it done. The owners are suggested owners, our recommendation, so adjust them to the roles your firm has.

Step Decision owner (suggested) Done when
1. Account structure and home region The CIO or IT head decides, with the platform lead. Every account sits under one parent with a named owner, and its home region is on record.
2. Identity The security lead decides. Every sign-in runs through the central identity source, and no shared admin login remains.
3. Network The network lead decides. The range plan shows no overlap, and name lookups work from a test account.
4. Central logs The security lead decides, with compliance or legal. Logs from every account reach the archive, and workload teams can read them but not delete them.
5. Guardrails The security lead decides, with the platform team. The platform refuses a test attempt to create public storage, and the logs show the refusal.
6. Cost tags Finance decides, with the platform lead. A test cost report groups spend by owner tag, with no untagged lines.
7. Pilot workload The pilot’s application owner decides, with the platform lead. The pilot runs in its own account with logs, tags and guardrails in place, and its owner signs it off.

Before You Build a Landing Zone: Scope, Team and a Signed Design

Settle three things before the first account opens: how big the first version is, who builds it, and which design they build to. A team that skips them can end up writing code before there is a plan.

First, size the first version to the workloads that will land first. If no workload needs a link to an on-premises site yet, leave room for that link in the plan and build it later. A first version that tries to cover every future case takes longer to agree and is harder to test.

Next, staff the build team with people who know security, identity, network and operations. At kickoff, the sponsors set the scope and make the high-level choices. The way to build the base is one of them, covered in the build routes a sponsor group can pick from, side by side. Those include how many environments to run and which regions are in play. As a result, those choices stay out of later build sessions.

Then write a design document that records each decision, and have the sponsors approve it before any build work starts.

Keep a short record of each decision

Each record holds a title, the context, the decision, its consequences and its status. Keep it where every team can read it. A year later, when someone asks why the network looks the way it does, the record answers.

How to Build a Landing Zone, Steps 1 to 3: Structure, Identity and Network

Steps 1 to 3 lay down the parts that every later control depends on. For a team that has to build a landing zone on an empty platform, these three come first.

Step 1: Set the Hierarchy and the Home Region

Start with the hierarchy, because every later control attaches to it. Place all accounts under one parent, then split them into production, non-production and shared services. A mistake in a test account then stays away from production.

How to build a landing zone account tree as three cards under one parent: production, non-production and shared services, in white, light gray and orange
Every new account opens in one of these three branches.

Shared services hold a platform area that the platform team runs, with identity, the network hub, logs and security tools. Workload areas sit beside it, one per team or application. Teams ask for a new one through a set request route instead of opening it themselves. That route keeps the tree whole as the firm grows.

Next, choose the home region for each area, and check that choice against the rules that apply to your data. In India, the Digital Personal Data Protection Act, 2023, in section 16, allows the Central Government to restrict, by notification, transfers of personal data to places outside India that it names. Under the government’s commencement notice of 13 November 2025, the section comes into force 18 months after that date, so it is not yet in force as of November 2026. The section does not on its own require data to stay in India. It also leaves any stricter Indian law on transfer in place, including sector laws. In the GCC, check your country’s data protection law and your sector regulator before you choose.

Done when: every account sits under one parent with a named owner, and its home region is on record with the reason for it.

Step 2: Identity Before Anyone Gets Access

Identity comes second. Access rules need the accounts to exist, and nobody should work in those accounts before sign-in is central.

Five ticked identity items for a new cloud account: one identity source, multi-factor sign-in, baseline roles, no shared admin logins and a protected emergency login, in white, light gray and orange
Five identity items to finish before any team starts work in an account.

Connect every account to one identity source, such as the directory your staff already use to sign in. Turn on multi-factor sign-in for everyone, starting with administrators. Then define a small set of baseline roles, for example read-only, developer and administrator, that each new account inherits when it opens. As a result, a team gets the same roles in its fifth account as in its first.

Remove shared admin logins as well. That includes the first all-powerful login created with the platform. Protect it with multi-factor sign-in, keep it for emergencies, and name the person who holds it. For the ideas behind this step, see identity and access management.

Done when: every sign-in runs through the central identity source, and no shared admin login remains.

Step 3: Network Address Ranges and Name Resolution

The network comes third. Networks attach to accounts, and identity decides who may change them.

Plan address ranges for every region you expect to use before you create the first network. Give each environment and region its own block, and keep the plan in one place. Add the ranges your offices, data centers and partner links already use, since a clash with those blocks a link as well.

Overlapping ranges are hard to undo

Two networks with overlapping ranges are hard to join later. The fix can mean renumbering or rebuilding one of them.

Then build a shared hub in the platform area for traffic that leaves the cloud, such as links to offices, data centers and the internet. Workload networks connect through the hub, which gives one place to inspect and control that traffic. The idea behind this split is network segmentation.

Plan name resolution (DNS, the service that turns names into addresses) in this step as well. Decide which names resolve inside the cloud, which resolve on premises, and how each side finds the other. A team that adds DNS after workloads arrive can end up fixing lookups one application at a time.

Done when: the range plan shows no overlap, and name lookups work from a test account.

How to Build a Landing Zone, Steps 4 and 5: Logging and Guardrails

Steps 4 and 5 set the records and the rules. When you build a landing zone, this pair runs in a fixed order: logs first, then guardrails.

Step 4: Central Logs in a Separate Archive

Logs come before guardrails, so that every action a guardrail blocks or allows leaves a record from the first day.

Create a log archive area in the shared services part of the tree. Its storage should be one that only a small group can change and that no workload team can delete from. Send activity logs and sign-in logs from every account there. Also keep a separate audit area for security tools, so the people who review alerts do not also manage the archive.

Then set retention from the rules that apply to you. In India, a log rule sits in item (iv) of CERT-In’s Directions of 28 April 2022. It names five groups: Government organizations, data centers, intermediaries, service providers and body corporate. Each of them must switch on logs for all its ICT systems. It must also store those logs securely for a rolling 180 days within Indian jurisdiction. Ask your legal or compliance lead whether your firm falls in one of those groups. For readers in the GCC, retention follows the local regulator instead. Where the 180-day rule applies, keeping those logs within Indian jurisdiction also feeds back into the home region choice from Step 1.

Done when: logs from every account reach the archive, and workload teams can read them but not delete them.

Step 5: Guardrails Written as Code

Guardrails come fifth. They need the hierarchy to attach to, identity to know who acted, and logs to report into.

A guardrail is a rule the platform applies to every account under one branch of the tree. Start with rules that block risky set-ups at creation, such as storage open to the public internet or logging switched off. A set-up blocked at creation does not reach production, so nobody has to find and fix it later.

Trial the policy method first

Try your way of managing policies in a test landing zone before the real one. In Signisys’s working view, the method you pick may be hard to change once many accounts rely on it.

Keep each rule narrow, too. A broad rule that blocks too much pushes teams to ask for exceptions. In turn, a pile of exceptions is harder to review than a few precise rules. Finally, write every guardrail as code, kept in version control and changed through review, so the live rules match the written ones. For the tooling side, see writing each layer as reusable code.

Done when: the platform refuses a test attempt to create public storage in a test account, and the refusal appears in the log archive.

Key Takeaway Central logs go in before the first guardrail, and every guardrail lives in code that goes through review.

How to Build a Landing Zone, Steps 6 and 7: Cost Tags and the First Workload

Steps 6 and 7 are where a plan for how to build a landing zone meets real spend and a real workload. Tags come first, then the pilot.

Step 6: Cost Tags Set Before Spend Starts

Tags come before any workload, because spend that carries no tag from day one has no owner later. A tag is a label, such as owner or environment, attached to each resource.

Agree a short required tag set with finance. Owner, cost center and environment answer the first questions finance asks about spend. Keep the list short, since each extra required tag is one more thing a team can get wrong. Then set a tag policy that checks new resources against the set and reports the ones that miss it. Budget alerts per account are also worth adding at this step, with limits that finance sets.

Write the tag set into the same code as the guardrails. That way, a new account gets it without anyone having to remember.

Done when: a test cost report groups spend by owner tag and shows no untagged lines.

Step 7: One Pilot Workload Through a Test Landing Zone

The pilot comes last, because it tests every earlier step on something real.

Pick the pilot early, during scoping if you can. Choose one that is low risk but still uses the parts you built: sign-in, network, logs and tags. For example, an internal tool with a small user group fits better than a customer-facing system.

Keep a second, test landing zone beside the real one. Run the build code against it from scratch, then destroy it and run it again. Each clean run shows the code can rebuild the base, while each failure points to a manual step nobody wrote down.

Next, move the pilot into its own workload account and check each earlier step’s done-when test against it. Fix any gap before the next workloads join, since every later team inherits whatever the pilot uncovered and nobody fixed. To score the finished base afterward, use scored checks with evidence for a finished cloud base.

Done when: the pilot runs in its own account with logs, tags and guardrails in place, and its owner signs it off.

Key Takeaway Fix every gap the pilot finds before the next team moves in. Each later account inherits the same base.

How to Build a Landing Zone When Workloads Already Run

Build the new structure beside the old accounts, then move workloads across in waves instead of rebuilding in place. A firm that has to build a landing zone while its systems stay live follows the same seven steps. Its pilot comes from existing workloads. Meanwhile, the old accounts keep running while the new base takes shape.

1
Pilot first

one low-risk existing workload moves first and passes every done-when test.

2
Waves by risk

the remaining workloads move in groups, lowest risk first.

3
Same tests for each wave

sign-in through the central source, logs in the archive, tags on every resource and guardrails applied.

4
Move or rebuild

decide for each old account, and record the reason.

5
Close the empty accounts

close each one, or bring it under the parent with the same rules as the rest.

A wave counts as moved only once it passes those tests. One that fails stays where it is until the team fixes the gap.

Some old accounts can move under the new parent as they are, after a review of their sign-ins and networks. Others hold years of manual changes, and rebuilding their workloads in fresh accounts is cleaner. An empty account left outside the tree is one more place nobody watches.

Moving each workload also has its own steps, from testing to cutover, and the checks for each move itself cover those.

Four Build Mistakes to Catch Early

Four mistakes are worth checking for before each step closes. Each one is easy to miss on a first build, and each is harder to fix once workloads depend on it.

DNS left out of the network step
Lookups between the cloud and on-premises sites fail, and teams patch them one by one. Plan name resolution in Step 3.

No tags at the start
Spend from the first weeks has no owner, and tagging it later means chasing each team. Set the tag policy in Step 6, before the pilot.

Manual changes that drift from the code
A quick console fix makes the live set-up differ from the code, and the next run may undo it or fail. Route every change through review, and check for drift on a schedule.

One region only
A base in a single region has nowhere to recover to if that region goes down. Plan a second region in Step 1 and reserve its ranges in Step 3.

Outside This Build Order, and When to Bring In Help

This guide covers the build order only. It leaves out scored checks of a finished base, the choice of build route, and what goes wrong in workloads already running.

Get specialist help when the residency rules for your sector are unclear, or when old accounts hold workloads nobody fully understands. Help also makes sense when your team has no one for one of the four build areas: security, identity, network or operations.

As a disclosure, Signisys provides cloud architecture, reliability and resilience work, and our cloud services and platform engineering team takes on this kind of work. A consultation covers your current accounts, the build order that suits them and the owners to name. No charge, with a fixed scope.

Book a consultation
Plan your landing zone build with Signisys

How to Build a Landing Zone: FAQ

Can identity come before account structure?

Not in this order. Baseline roles attach to accounts, so the accounts need to exist first. You can connect the identity source and switch on multi-factor sign-in while the structure is being agreed. However, apply roles only once each account sits under its parent, or you will reassign them later.

Does a small firm need all seven steps to build a landing zone?

Yes, although each step can be small. A firm with a few accounts may need only three environments, a handful of roles, one range plan and three tags. The order still matters, since skipping logs or tags early leaves gaps that grow with each new account. Size each step to the first workloads, as the scoping section describes.

Who should look after the landing zone once it is built?

We recommend a named platform lead or platform team, with the security lead owning guardrails and logs, and finance owning the tag set. Changes go through the same code and review as the build. Teams also request new accounts through the route from Step 1, which keeps the tree whole as the firm grows.

Does a landing zone need more than one cloud region?

That depends on your recovery needs and the residency rules that apply to your data. A second region gives you somewhere to recover workloads if the home region has an outage. Where data has to stay in one country, check that your provider has a second region there before you plan on it. Either way, reserve address ranges for a second region in Step 3.

Newsletter

Security Insights, Delivered.

Practical, vendor-neutral analysis of threats, tools, and architecture decisions.

Book a Consultation

A practice principal will contact you within 1 business day.

Thank you! A Signisys principal will be in touch within 1 business day.